Plant 134 Membrane Replacement

Man switching membranes

Plant 134, the District’s surface water treatment facility, operates five water filtration trains, each equipped with 180 membrane filters. The membrane manufacturer recommends replacement every 5 to 7 years to maintain treatment efficiency and reduce maintenance needs.

Beginning in FY 2017-18, the District initiated a phased replacement of the membranes, replacing one train per year over four years. Replacement of the fifth train was deferred due to funding priorities and improved in-house repair capabilities, with those membranes ultimately replaced in FY 2023-24. In FY 2025-26, the District will restart the membrane replacement cycle, beginning with Train 1, which has now been in service for seven years. A budget of $350,000 has been allocated for this work.

2025-26 Fiscal Year Cost

$350,000


Project type

Water


Current Phase

Construction


Projected Completion

June 2030


Location

District's Surface Water Treatment Facility